Concreting finished - 12 tonnes, four days!
...including three window cills.vendredi 31 mai 2024
dimanche 26 mai 2024
sheep shearing
Two six hour concreting shifts and about 3/5 of the barn floor is laid. Another cubic metre tomorrow then I need more cement and ballast for the last section.
Sheep shearing is tomorrow and as normal 4 sheep sheep refused to go in the barn. Two and a half hours of chasing them and finally they're in. minutes before the drizzle started, so we should be good to go tomorrow.
Managed to get a brand new scaffold tower on "leboncoin" and saved myself 300 euros. The seller was a bit dodgy, but as long as I paid cash all was good. The scaffolding is still in its original plastic unopened wrapping. The plans for the barn construction stages are slowly taking shape, hopefully we'll be watertight and re-roofed before the end of the year.
jeudi 23 mai 2024
mercredi 15 mai 2024
more progress
A trip to the natural granite sand pit with the tractor and sieve this morning, then a bit of pointing (still wet). Will probably mix and pour the ground floor concrete slab next week.
lundi 13 mai 2024
Cour Vic
At the weekend the pipework for the below ground services (water, electricity and sewerage) were put in the barn - hard work and another mountain of rocks removed. The floor is now levelled and blinded, ready for insulation, DPM and concrete slab.